Ahmedabad Airport records fastest re-carpeting work! 3.5 km runway re-carpeted in 75 days
Ahmedabad Airport records the fastest runway re-carpeting work! The re-carpeting work on the 3.5 kilometre long runway of Ahmedabad’s Sardar Vallabhbhai Patel International Airport in Gujarat has been completed in just 75 days, the airport operator- Adani group said on Thursday. According to the airport operator, for re-carpeting the Ahmedabad Airport’s runway, two lakh metric …